Work · 186 handovers since 2014

Six projects, with what went wrong on each.

Size, programme, contract value, and the one thing that made each job difficult. A portfolio that only shows the photograph is a portfolio that has not told you anything.

Boutique, Dubai Mall
01 · RETAIL

Boutique, Dubai Mall

AREA

1,150 sq ft

PROGRAMME

9 weeks

VALUE

AED 940 k

Night-shift only. The shopfront glazing was craned in through the service corridor at 03:00 because it would not pass the mall doors.

Flagship, City Walk
02 · RETAIL

Flagship, City Walk

AREA

3,400 sq ft

PROGRAMME

13 weeks

VALUE

AED 2.6 m

Two levels connected by a stair we built in the workshop and installed in three pieces overnight.

Restaurant, DIFC
03 · F&B

Restaurant, DIFC

AREA

2,600 sq ft

PROGRAMME

17 weeks

VALUE

AED 3.4 m

Grease duct routed 42 m to the riser. That single line is why an F&B programme is never twelve weeks.

Family villa, Al Barari
04 · RESIDENTIAL

Family villa, Al Barari

AREA

7,800 sq ft

PROGRAMME

22 weeks

VALUE

AED 4.1 m

Full MEP replacement in an occupied compound. Works stopped every day at 18:00 by agreement with the neighbours.

Office floor, One Central
05 · COMMERCIAL

Office floor, One Central

AREA

5,200 sq ft

PROGRAMME

11 weeks

VALUE

AED 1.9 m

Cat B on a live floor. Fire alarm cause-and-effect retested twice because the base build drawings were wrong.

Showroom, Al Quoz
06 · RETAIL

Showroom, Al Quoz

AREA

4,600 sq ft

PROGRAMME

12 weeks

VALUE

AED 1.5 m

Our own neighbourhood. Joinery walked across the road from the workshop rather than being trucked.

PARTITIONS ◦JOINERY ◦STONE ◦MEP FIRST FIX ◦CEILINGS ◦SHOPFRONTS ◦CIVIL DEFENCE NOC ◦SCREED ◦VENEER ◦GLAZING ◦COMMISSIONING ◦SNAGGING ◦PARTITIONS ◦JOINERY ◦STONE ◦MEP FIRST FIX ◦CEILINGS ◦SHOPFRONTS ◦CIVIL DEFENCE NOC ◦SCREED ◦VENEER ◦GLAZING ◦COMMISSIONING ◦SNAGGING ◦