The build itself is predictable. What is not predictable is Dubai Municipality, the mall, Civil Defence and a stone quarry in Carrara — so those are named here with their real durations.
This is the programme we issue at tender, not a marketing version of it. The orange bars are the ones sitting in someone else's queue — an authority, a landlord, a stone supplier — and they are where a twelve-week job becomes a sixteen-week one.
Survey & design freeze
BINAA + DESIGNER
Landlord / mall approval
LANDLORD
Authority submission
DM / TRAKHEES / DDA
Joinery shop drawings
BINAA WORKSHOP
Strip-out & partitions
BINAA SITE
MEP first fix
BINAA MEP
Joinery manufacture
AL QUOZ WORKSHOP
Ceilings, screed, finishes
BINAA SITE
Joinery install & stone
BINAA SITE
MEP second fix & testing
BINAA MEP
Civil Defence NOC
CIVIL DEFENCE
Snagging & handover
BINAA + CLIENT
ORANGE = OUTSIDE OUR CONTROL · DRAG OR SCROLL SIDEWAYS
Week 1–2 · demolition, partitions set out to the approved drawing
Week 3–5 · ducting, containment, drainage — everything you never see again
Week 6–9 · plaster, screed, stone, and the joinery arrives from Al Quoz
Week 10–12 · commissioning, Civil Defence NOC, snagging, keys