Programme & approvals

Twelve weeks, and the six queues you sit in.

The build itself is predictable. What is not predictable is Dubai Municipality, the mall, Civil Defence and a stone quarry in Carrara — so those are named here with their real durations.

Programme · retail unit, 12 weeks

Every bar has an owner. Four of them are not us.

This is the programme we issue at tender, not a marketing version of it. The orange bars are the ones sitting in someone else's queue — an authority, a landlord, a stone supplier — and they are where a twelve-week job becomes a sixteen-week one.

W01
W02
W03
W04
W05
W06
W07
W08
W09
W10
W11
W12

Survey & design freeze

BINAA + DESIGNER

BINAA

Landlord / mall approval

LANDLORD

EXTERNAL

Authority submission

DM / TRAKHEES / DDA

EXTERNAL

Joinery shop drawings

BINAA WORKSHOP

BINAA

Strip-out & partitions

BINAA SITE

BINAA

MEP first fix

BINAA MEP

BINAA

Joinery manufacture

AL QUOZ WORKSHOP

EXTERNAL

Ceilings, screed, finishes

BINAA SITE

BINAA

Joinery install & stone

BINAA SITE

BINAA

MEP second fix & testing

BINAA MEP

BINAA

Civil Defence NOC

CIVIL DEFENCE

EXTERNAL

Snagging & handover

BINAA + CLIENT

BINAA

ORANGE = OUTSIDE OUR CONTROL · DRAG OR SCROLL SIDEWAYS

Authority approvals

Who you are waiting for, and for how long.

Dubai Municipality10–20 working daysBuilding modification permit for anything touching partitions, MEP or drainage.
Trakhees10–15 working daysFor units inside Jebel Ali, Dubai South and other Ports & Customs jurisdictions.
DDA10–15 working daysDesign District, Studio City, Production City and the rest of the TECOM communities.
Civil Defence NOC5–10 working daysBooked, not requested. Required before you can open, no exceptions.
Mall landlord5–25 working daysThe widest variance of anything on this list, and nobody can compress it.
DEWA connection7–15 working daysOnly if the load changes. Most fit-outs do not need it; F&B always does.
The four stages

What is happening on site.

01Strip-out & framing

Week 1–2 · demolition, partitions set out to the approved drawing

02MEP first fix

Week 3–5 · ducting, containment, drainage — everything you never see again

03Ceilings & finishes

Week 6–9 · plaster, screed, stone, and the joinery arrives from Al Quoz

04Handover

Week 10–12 · commissioning, Civil Defence NOC, snagging, keys