Six jobs, with the concrete volumes.

Value, duration, status and the numbers that describe the build — cubic metres placed, floor cycle, snag count, slab flatness. Including the school we handed over three weeks late and paid AED 1.4 m of liquidated damages on.

Residential tower, JVC
level 24 poured 6 days early
jvc_tower_b[on_site]

Residential tower, JVC

Private developer · Substructure + superstructure + MEP

Height

G + 38 + roof

Concrete

46,200 m³ placed to date

Peak workforce

612

Cycle

6 days per floor

AED 214 m31 months

Two tower cranes, a 6-day floor cycle, and a raft pour of 4,100 m³ in a single 22-hour placement. The pour is the number worth checking on any contractor: continuous placement means no cold joint, and it takes eleven months of planning to achieve.

School, Al Barsha South
handed over 3 weeks late — LDs paid
al_barsha_school[handed_over]

School, Al Barsha South

Education operator · Full construction, external works

Area

18,400 m² GFA

Capacity

1,450 pupils

Delay

3 weeks

LDs

AED 1.4 m, paid

AED 96 m22 months

Three weeks late, and we paid the liquidated damages without argument. The cause was ours — a late structural steel order for the sports hall — and it is on this page because a contractor who has never paid LDs has either never been late or never told you.

Logistics warehouse, DIP
slab flatness FM2 achieved
dip_warehouse[handed_over]

Logistics warehouse, DIP

3PL operator · Design & build, PEB structure

Area

31,000 m²

Clear height

12 m

Slab

FM2 flatness, laser screed

Docks

24

AED 61 m14 months

A warehouse is a floor slab with a roof over it. Get the flatness wrong and the client's VNA forklifts cannot reach the top pallet — which is why the slab, not the steel, is where our attention went.

Villa compound, MBR City
snag list closed at 94%
mbr_villas[defects_liability]

Villa compound, MBR City

Family office · 24 villas + infrastructure

Villas

24, four typologies

Plot

9.2 ha

Snags at handover

1,180

Closed within 60 days

94%

AED 148 m26 months

We publish the snag count because everyone has one. Eleven hundred snags across 24 villas is normal; what matters is that 94% closed inside sixty days and the rest were tracked openly rather than argued about.

Roads & infrastructure, Meydan
utilities diverted around live DEWA 132kV
meydan_infra[handed_over]

Roads & infrastructure, Meydan

Master developer · Roads, storm water, utilities

Roads

6.4 km

Storm water

3.1 km

Live diversions

11

Downtime caused

0 hours

AED 73 m18 months

Eleven live utility diversions around a 132 kV DEWA feed with no outage. Infrastructure work is judged on what did not happen, which makes it impossible to photograph and easy to undervalue.

Hotel extension, Deira
hotel stayed open — 0 guest complaints logged
hotel_ext[handed_over]

Hotel extension, Deira

Hospitality group · Structural extension, occupied site

Keys added

88

Site status

Occupied hotel

Noisy works

10:00 – 16:00 only

Complaints

0 logged

AED 42 m16 months

Building next to paying guests means a six-hour noisy-works window and a programme that assumes it. Contractors who price this like an empty site lose money in month three and start asking for variations.